The Washington Times
  • Subscribe
  • Times News Services
  • RSS
  • Mobile Headlines
  • e-edition
  • E-MAIL ALERTS
  • REGISTER
  • LOG IN
  • E-MAIL ALERTS
  • WELCOME
  • Your Profile
  • Log Out
  • Front Page Image
  • Classifieds
  • Autos
  • Real Estate
  • Jobs
  • Special Sections
  • Customer Service
  • Home
  • News
  • Opinion
  • Sports
    • NFL
    • NBA/WNBA
    • MLB
    • NHL
    • Tennis
    • Golf
    • Motorsports
    • Soccer
    • NCAA
    • Olympics
    • Outdoors
    • Other
  • Culture
    • Home & Living
    • Family & Kids
    • Fashion
    • Food
    • Travel
    • Health
    • Washington Visitors
    • Books
    • Military History
    • Life
    • Auto
    • TV Listings
    • Movie Listings
    • Death Notices
    • Entertainment
  • Themes
  • Communities
  • Marketplace
    • Autos
    • Jobs
    • Real Estate
    • Classifieds
    • Shopping
    • Dining Out
    • Education
    • TWT Store
  • Videos
    • Two Guys
    • Birnbaum on Washington
    • Liz Glover
    • Amanda Carpenter
    • Morning Briefing
    • Documentaries
    • Joe Giganti
    • Video Game Minute
  • Podcasts
    • About Headlines
    • Audio and Radio
    • America's Morning News
  • NFL

    Same old problems plague Redskins

  • Politics

    Obama: It's Senate's turn on health care

  • Security

    Army chief wary of backlash against Muslim soldiers

  • Sports

    Offense erupts in Caps' victory

  • National

    KUHNHENN: 10% jobless rate is Obama's troubling world

  • World

    Joint forces probe NATO air strike

  • National

    Fla. shooting suspect 'mentally ill'

Thursday, March 27, 2008

The scores of city officials, construction workers and architects working on the Washington Nationals' new ballpark grew accustomed to one thing over the last two years: pressure.

Rate this story

Average 0.00
after 0 votes
Login or register to rate this story

  • Font Size -+
  • Print
  • Email
  • Comment
  • Tweet this!
  • Share
  • Article
  • Comments ()
  • Click-2-Listen
  • Videos

More Stories

  • Suicide bomber kills 12 in Pakistan market
  • Abortion takes driver's seat in debate
  • School lunch risk eyed after E. coli outbreak
  • Same old problems plague Redskins

By

The scores of city officials, construction workers and architects working on the Washington Nationals' new ballpark grew accustomed to one thing over the last two years: pressure.

From the start, there was pressure all around the stadium project. Deadline pressure. Budget pressure. Political pressure.

But on March 30, Nationals Park will host its first official Major League Baseball game, just 23 months after the start of construction — record pace for the building of a major league stadium. What's more, the project will be completed without violating the D.C. Council's $495 million cap on the "hard" and "soft" costs such as labor, materials, financing and insurance.

"I'm pleased we were able to get it open on time and keep it under the cost cap, but I knew all along we would," said council member Jack Evans, Ward 2 Democrat and stadium advocate. "So I'm not surprised, but I'm pleased we were able to do it."

Officials have been quick to credit the thousands of workers who toiled along South Capitol Street for the last two years, but many of the decisions that allowed the city to complete the project on time came early on, starting with the D.C. Sports and Entertainment Commission's selection of HOK Sport as lead architect and Clark Construction as lead builder.

HOK had built many of the newer ballparks in Major League Baseball, and Clark headed several large construction projects, including FedEx Field and the Walter E. Washington Convention Center. The commission also added local architect Devrouax & Prunell and Hunt Construction Group and Smoot Construction.

"You have to be working with architects and designers and builders who know what ... they're doing," said former sports commission CEO Allen Lew, who left the post last year to head the city's school modernization efforts. "These people have to be experts, they have to have a proven track record and understand the idea of fast-tracking. You bring in contractors and builders that are willing to accept the deadlines and the challenges."

In a traditional construction project, architects complete their plans before handing them over to the builder. But with the construction of Nationals Park, there was no time for waiting.

"In this case, instead of taking a foot of contract drawings, we took an inch," Clark project executive Matt Haas said. "In many cases, we couldn't wait for the drawings and just [had] to rely on our experience to do the right thing."

Clark had done this type of accelerated work before, but the company still was working uncertain territory, particularly when it came to helping craft a cap on the cost of construction to satisfy the D.C. Council.

It was around Christmas in 2005 when Lew requested that Clark perform the construction work for a guaranteed, fixed price. But Clark had not yet selected its subcontractors and had only just started to outline its budget. Lew said he needed a hard number by Jan. 21.

"We were like, 'Wow, Allen, that's nearly impossible,' " Haas said. "And he said, 'All right, I'll give you another week.' And so by the end of January — basically a month — we had to pull this whole thing together."

The Clark/Hunt/Smoot team guaranteed it could build the ballpark on time for $320 million in hard costs. But that price was contingent on locking down a price for steel, which was quickly becoming an expensive commodity.

Lew responded by placing an order for the steel even before the council voted on the stadium lease. The penalty for canceling the order was $60,000, but Lew's gamble paid off when the council and baseball officials finally gave the go-ahead. Groundbreaking took place in May 2006, and the steel arrived on Oct. 5, one day ahead of schedule.

Construction remained essentially on course from then on, thanks in part to daily meetings at the ballpark site with the contractors, architects and workers. Senior officials from the Nationals, Clark and the sports commission met every Thursday.

"There's just no time to wait for answers here," Haas said. "You literally have no time for answers. Hundreds of problems come up a day that have to get solved, and they have to get solved that day."

And budget pressure was constant. The costs of cleaning up the stadium site and acquiring land, the funds for which were not capped, went more than $40 million above estimates. The cost to build parking on the site was $11 million more than anticipated. Sidewalks cost $7 million more and site work on the stadium's south end rose $2.5 million above projections. There were times when contingency money dipped to only a few million dollars.

But there were savings elsewhere. The city saved $17 million on the cost of financing the ballpark. Installation of utilities cost $3 million less than expected. In all, the stadium will be completed with about $10 million to spare.

"It's been a collaborative effort," said Greg O'Dell, the current CEO of the sports commission. "There's definitely been a lot of project management that people don't see. On projects like this you need to have everybody at the table to address issues in real time. It doesn't just happen. It's been a very well-executed strategy."

Post a comment

There are comments on this article, submit your opinion!

Please login or register to post a comment

Ask a Question

You Report

Do you have another point of view, photos, audio, video or more information about a story?

Top Stories

Most Read

  1. EXCLUSIVE: Rare virus poses new threat to troops
  2. Parents buying homes for kids at college
  3. EDITORIAL: Too scared to recognize terrorism
  4. House OKs health reform bill
  5. Inside the Beltway
More Top Stories »
  1. Sniper's ex-wife speaks out on abuse
  2. Annandale man killed in hit-and-run
  3. Aborted fetus cells used in beauty creams
  4. Sunshine vitamin stirs new debate
  5. PRUDEN: Corpse sits up, gets nice salute

Most Shared

  1. Parents buying homes for kids at college
  2. EXCLUSIVE: Rare virus poses new threat to troops
  3. EDITORIAL: Too scared to recognize terrorism
  4. Sunshine vitamin stirs new debate
  5. Obama's unlearned lesson
More Top Stories »
  1. NSA surveillance -- of you?
  2. Aborted fetus cells used in beauty creams
  3. PRUDEN: Corpse sits up, gets nice salute
  4. EDITORIAL: The negative Obama factor
  5. Israelis unsure of U.S. support

Most Commented

  1. House OKs health reform bill
  2. EDITORIAL: Too scared to recognize terrorism
  3. Furious scramble for health reform support
  4. Muslims stunned by Fort Hood shooting
  5. 'Gentle' Army psychiatrist displayed worrisome signs
More Top Stories »
  1. Obama praises those who ended Fort Hood violence
  2. Army chief wary of backlash against Muslim soldiers
  3. Making fun of faith
  4. Israelis unsure of U.S. support
  5. Obama: It's Senate's turn on health care

Listen to Washington Times Radio

  • America's Morning News

    with John McCaslin and Melanie Morgan

Blogs & Columns

  • POTUS Notes

    New Dem talking point on Obama approval doesn't wash

  • The Back Story

    12 arrested at Pelosi's office

  • Belief Blog

    Washington goes Greek this week

  • Out of Context

    Foods that might kill libido

  • Technology

    Facebook wins round against phishing spammer

  • On the Fly

    United lifts some 'award' blocking

  • Redskins 360

    Samuels feeling better, hopeful

  • Tara's Two Cents

    On their way to summer vacation..

  • SNOBlog

    Beyond 'Woody'

Videos

Advertising Links
TWT Store
  • e-edition
  • Print Edition
  • Weekly Washington Times
TWT Affiliates
  • Middle East Times
  • Golf
  • UPI
  • Arbor Ballroom
  • Washington Times Global
  • About TWT
  • Press Room
  • F.A.Q.
  • Work for TWT
  • Advertise
  • Sponsors
  • Contact Us
  • Privacy Policy
  • Site Map

All site contents © Copyright 2009 The Washington Times, LLC.